AMPYR in partnership with Green Gold Energy (GGE) are developing the Northern Battery in Port Augusta to provide South Australia with energy reliability and security through energy storage.
270 MW
1,080 MWh battery size which is configured to operate as an 8 hour BESS when required
45000
homes powered during peak demand periods when renewables are not producing
120 +
jobs expected to be created during construction
Northern Battery
The Northern Battery will comprise around 248 batteries and 64 inverters in rows, delivering a nameplate capacity of 270 MW, with a total storage capacity of approximately 1080 MWh. A new substation will be developed adjacent to the battery area and connected to the existing Davenport substation via a new underground transmission line.
The project will also include ancillary infrastructure such as storage buildings, staff amenities, stormwater ponds, and site fencing, with vehicle access provided via Augusta Highway and Northern Power Station Road to ensure efficient site operations.
The site of the Northern Battery was chosen with careful consideration to minimise impacts on the environment and residents of the Port Paterson area.

Location
The project is located approximately 6 km south of the centre of Port Augusta.
The project site formerly hosted the Northern Power Station, which was closed in 2016 and has subsequently been demolished. The BESS development site is less than 1% of the Northern Power Station site (approximately 7 hectares).
What is the planning approval process in South Australia?
A BESS development is assessed by the South Australian Department for Energy and Mining (DEM) and determined under the Hydrogen and Renewable Energy Act 2023 (HRE Act) by the Minister for Energy and Mining (the ‘Minister’). A BESS requires an Associated Infrastructure Licence (AIL) under the HRE Act.
To obtain an AIL, a developer must prepare an Environmental Impact Report (EIR) which describes the environmental conditions and potential impacts the development may have on the environment. A developer of a renewable energy facility, including a BESS development must avoid or reduce environmental damage as far as reasonably practicable. Managing environmental risks is outlined in the Statement of Environmental Objectives (SEO), which establishes criteria to be applied to various objectives. By way of example, noise generation may be considered an environmental risk and there will be criteria which would be applied to ensure that any potential noise is managed appropriately.
The draft EIR will be supported by a range of expert environmental reports, which is likely to include acoustic, visual, native vegetation, cultural heritage, traffic and stormwater/civil assessments. The outcomes of these technical reports will inform the management of the environment for the construction and operation of the development and will inform the SEO.
DEM published the EIR & SEO documents for public consultation which concluded on March 30th 2026.
Community
AMPYR is committed to working with local communities to support jobs and business opportunities, avoid and minimise impacts and deliver lasting benefits for local people.
Community Benefit Fund
Over $40,000 of funding was provided during the 2025 round of the Northern Battery Community Benefit Fund. We will be excited to launch the second round later in 2026.
For more information about the Community Benefit Fund, click here.
Empowering Australia’s First Nations
AMPYR is committed to partnering with local First Nations communities to respect culture and Country, support local jobs, business and training, and delivery legacy benefits for the community.
AMPYR is also committed to pursuing equity partnerships with local First Nations communities, where this delivers benefits for the project and the community. Equity stakes in AMPYR can deliver 20+ year revenues, support First Nations economic empowerment and self-determination.
Frequently Asked Questions
Noise
Will I be able to hear the battery facility from my home?
No, you shouldn’t hear anything. With the noise control measures in place, the sound at the nearest home will be around 38 dB (decibels). For comparison, a normal conversation is about 60 dB.
Will it be noisier during the day or at night?
The assessment predicts relatively consistent noise levels of approximately 38 dB at the nearest residence during both day and night periods. However, operational noise can vary depending on the battery discharge rate and ambient temperatures at the site.
How far away is the facility from the nearest homes?
The closest home is over 500 meters away. At this distance, the predicted noise level is 38 dB, which is well below the night & day limits.
Visual
Will I be able to see the battery facility from my property?
The facility sits in an excavated area 4–5 meters below ground level, making it largely invisible from surrounding properties. The assessment found negligible to low visual impact from all viewpoints assessed.
What will the facility look like and how tall are the structures?
The facility includes 208 battery units (2.6m height), 52 inverters, a substation with bus pipes (6–10m height), and 2.1m security fencing. The batteries are white shipping-container-style units.
What is being done to screen the facility from view?
A 5-meter-wide landscape buffer zone around the perimeter will include native trees and shrubs, with automatic irrigation during the establishment period and a minimum two-year maintenance program.
Vegetation
How much native vegetation will be cleared for this project?
The project will clear approximately 6.7 hectares of low coastal shrub land in very poor condition. The site is a former soil borrow pit that has been significantly disturbed, with much of the area consisting of natural regeneration rather than intact native vegetation.
What measures are being taken to avoid or minimise vegetation clearance?
The project site was selected because it is mostly free of native vegetation and already heavily degraded from past use as a borrow pit. The design avoids a small patch of better-quality vegetation in the northwestern corner, and the development footprint has been positioned in the most degraded areas of the site.
What will happen to the site after construction?
Natural regeneration is expected to occur around the facility infrastructure and along the transmission corridor after construction is complete. The site has a demonstrated capacity for natural regrowth, as evidenced by the vegetation that has regenerated since previous disturbance activities on the former borrow pit site.
Traffic
How much traffic will the battery facility generate during construction?
During the 18-month construction period, the facility will generate an average of 66 vehicle movements per day (combining light and heavy vehicles). Peak construction activity is expected to last approximately 6 months. Typical peak hour volumes would be around 20 movements, with the majority being light vehicles associated with construction staff. These volumes are considered very low and well within the capacity of the existing road network.
What access route will construction vehicles use to reach the site?
Construction vehicles will access the site via Northern Power Station Road, which connects to the Augusta Highway. The route utilizes existing internal access roads within the broader property to reach the battery facility location. Northern Power Station Road is currently approved for vehicles up to 36.5m Road Trains, though the private section of the road has a 4.3m height restriction that contractors will need to consider.
Will there be any traffic impact once the facility is operational?
Traffic during the operational phase will be extremely low, with less than one vehicle movement per day on average. Movements will primarily consist of routine inspections and maintenance visits occurring approximately 10 times per year, typically using light vehicles. This minimal traffic will have negligible impact on the surrounding road network.
Heritage
Are there any Aboriginal heritage sites that will be affected by this project?
No known Aboriginal heritage sites have been identified within or adjacent to the project area. The site has been extensively cleared and graded since 2016–2018, and heritage register searches confirm no recorded sites exist in this location.
What happens if Aboriginal artefacts or sites are discovered during construction?
All work must stop immediately if any Aboriginal heritage is found, as all sites are legally protected whether previously recorded or not. The discovery must be reported to the Minister for Aboriginal Affairs, and work cannot resume without proper authorisation.
Stormwater
Will stormwater from the battery site cause flooding on my property?
The site will include a detention basin that captures and slowly releases stormwater to ensure post-development flows don’t exceed current levels. Protective earthworks along the northern boundary will also prevent external floodwaters from entering the site.
How will water quality be managed from the industrial site?
All site runoff will flow through a swale into a detention basin that removes over 90% of sediment and pollutants before discharge. This exceeds EPA South Australia standards for total suspended solids (80%), phosphorus (60%), and nitrogen (40%).

















